Earth movement, civil Works, electromechanical and piping erection; electrical and instrumentation installation for the 3rd thickener. It also includes a Shaft with a new pump system, electrical room and others.
Earth movement, civil Works, electromechanical and piping erection; electrical and instrumentation installation for the 3rd thickener. It also includes a Shaft with a new pump system, electrical room and others.
Civil, Electromechanical and Structural Assembly corresponding to the expansion of the Lithium carbonate Plant and the Lithium Hydroxide Plant. "FastTrack" project with day and night shifts.
Propulsion system from well water zone up to water transfer tank and fresh water tank. Includes the installation of 10 Km of 8” Steel pipe and 6Km of 14” HDPE pipe, plus all associated civil Works. Located at more tan 4.400 m.a.s.l.
Supply and Erection works for the replacement of 20km of concentrate pipeline. Includes earth movements, civil works, piping (including liner insertion) ,electric and instrumentation.
Civil Works and associated Works for: - One Elevated Tailing Tank. - One washing water Tank.
Erection of the new columnar cells, including new compressor, samplers, pumps and the electrical & control installations, among others
Engineering, supply and construction of the dome and auxiliary systems. This project contemplates the transport of copper concentrate from the filtration plant to a reinforced concrete dome, where it is stored (30.000 metric tons), using a tubular conveyor belt. The concentrate is distributed by a stacker; a reclaimer takes it to the main hopper, unloading into two underground conveyor belts, which take the concentrate to the Roasting Plant.
Construction and assembly of a structural dome for the existing stockpile, built with a special condition: the overland conveyor belt never stopped, generating complex work conditions of dust due to the permanent wind. The dimensions of the dome were 117 m in diameter and 47 m height.
Basic and detail engineering, supply, construction and startup of the emissions abatement system for a furnace located in Planta Huasco. Consisted in the implementation of an electrostatic precipitator and a wet desulphurizer and auxiliary parts, for a gas flow of 500.000 Nm3/h.
Basic and detail engineering, supply and building of a sulfuric acid tank, train loading system and jetty extension.